Annual Function Check and Calibration of Flow Switches Low Low / FSLL (SWITCH FLOW LOW LOW STABILIZER HEATER):
Annual Function Check and Calibration of Flow Switches
Low Low / FSLL (SWITCH FLOW LOW LOW STABILIZER HEATER):
TASK TO BE
PERFORMED:
1. Annual Function Check and Calibration of Flow
Switches Low Low.
2. Inspect Flow Switch for any physical damage.
3. Ensure Flow Switch is securely mounted.
4. Check impulse lines are securely fastened.
5. Check drain valves are closed.
6. Inspect impulse lines connections for leaks.
7. Check manifold connections for leaks.
8. Check drain plug connections on Flow Switch body
for leaks.
9. Ensure drain valves are plugged and there are no
leaks.
10. Ensure differential switch glass is secured
correctly and is not cracked or broken.
11. Check differential switch pointer for any
pulsation.
12. Inspect electrical signal cable for any physical
damage.
13. Check cable gland is secure.
14. Inspect switches for any excessive wear on
actuating lever.
15. Inspect switches for any misalignment or damage.
16. Check all terminations are secure.
17. Open Bypass valve, isolate sensing lines, drain
and vent housings.
18. Note
19. Care should be taken during venting process as
some lines may contain hazardous fluids. PPE should be worn.
20. Check that the Flow switch indicates zero differentials,
adjust as required.
21. Calibrate Flow Switch to + or - 1% of range in
increments of 20% both rising and falling pressure, adjusting zero and span as
required.
22. Note
23 Switches, to be calibrated against Wallace and
Tiernan Pneumatic calibrator.
24. Adjust switch to the required set point.
25. Check that the Switch has activated. Adjust as
required.
26. Check that the Low Low Alarm has been received in
control Room.
27. Repeat steps 20 TO 26 till correct set point has
been obtained.
28. Complete Instrument Calibration Sheet.
29. Ensure all drain points are securely closed off.
30. Check all disturbed connections for leaks using
soap solution.
31. Complete Instrument Calibration Sheet.
32. Affix calibrated Flow switch with label giving
date of calibration and tag number.
33. De-isolate sensing lines and close by-pass valve.
34. Return Pressure Differential switch to service.
35. ENSURE ANY OVERRIDE IS REMOVED AND AUGUST SYSTEM
RETURNED TO NORMAL MODE.
36. Sign-off Work Permit and return to operations.
37. Report all findings to supervision and document in
CMMS.