LEVEL CONTROL LOOP 6 MONTHLY Preventive Maintenance LCV (VALVE LEVEL CONTROL INJECTION COMPRESSOR)
SAFETY
PRECAUTIONS
Before performing any task you
must have a PERMIT TO WORK (PTW).
Observe all safety precautions
and any additional requirements as per work permit.
Advise control room operators
before starting LEVEL CONTROL LOOP and alarm check.
TASKS TO BE
PERFORMED:
1. Function check the LEVEL
CONTROL LOOP by operating the controller. PCV must be on bypass.
2. Visually check LCV and LIC
make sure the valves move smoothly. Ensure that the
LIC is on manual.
3. Function check the following
pump low pressure alarms by operating the appropriate switch: LSL, LSLL, LI;
and check calibration of all LT. Check level recorder and replace pens and
paper if need.
4. Record all set points.
5. Record any abnormality below
and advise supervisor.
6. Sign-off on all work orders
and permit.
7. Document any abnormality on
WO & in CMMS.